800 + 
Phase 1
internal Reordering

Fund
raising

Amount so far
– May 2023

£ 17 500 approx

Next Event

How can I help ?

We want as much help as you can give, with fund-raising, developing activities and, and, and . . .
contact us if you think you can help in any way.

Please add your stories, pictures and memories of Hook Church to our Treasure Trove . . .

Fundraise

Please contact Henry Cook with your ideas and help for fundraising.
(Henry’s co-ordinating these events & activities)

 

Write Letters of Support for the project telling us and our funders  what you imagine you’ll be able to put on here once Phase 1 is done.

Give,

either a one off donation or in a regular way, as an individual or from your company.

Making the Building fit for 21st Century use

Hook Church has undergone a number of changes down the centuries to make it suitable for the people of the day.

Most medieval churches had two distinct areas, a ‘holy’ or set-apart area in the ‘chancel’ which was only ever used for religious purposes and for many of the daily services. The ‘altar’ would have been by the East Wall. It would have been separated from the ‘nave’ or body of the church by a ‘rood screen’. (See Picture at the end of this page). The nave  was used for larger services with the people standing and often milling about and possibly a few benches by the walls where the elderly or infirm could sit. Hence the saying ‘our backs to the wall’. There would have been wall paintings and possibly stained glass which told the Bible stories and other religious messages. Many used these as much as the spoken words in their worship. At the reformation, most rood screens were removed along with any stone altars and many wall paintings and stained glass windows also removed. This was because of perceived corruption of the message and story of Jesus going on in the practice of the church before the reformation. Lecterns on which a church bible in the language of the people and a Holy Table in the Nave round which to share the Lord’s Supper were the new things and practices of worship changed significantly. By the time of the Victorians and the 1844 Restoration of the church, styles of worship were less ‘puritanical’ but did include long sermons and anthems by the local choir. Seating for the public to take part in these types of services was popular and cheap seating using ‘pews’ without cushions were installed in a ‘linear’ fashion, with all facing the choir / preacher. Today we have a wide range of worship styles popular and useful in the church of England, including forms which echo the medieval and forms which pick up on all sorts that’s happened before and since then. We also need communal space, somewhere or way that ‘people’ can meet together and form the family of God, not needed when the church served a small village in which everyone worked cheek by jowl and new one another. So we’re looking to re-order, again the inside of the church to allow us to worship and meet in a way which is suitable to our age.

We’re also aware that medieval churches not only served their community as a religious space, but when worship was not taking place in them the nave would be used as a public meeting room and for markets and so on. Now we don’t have ambition to have pigs in again, or use the church building in inappropriate ways, but we do want the building used day in day out by the community to help people live their lives better. So would like to have the Nave of the church returned to being a flexible space which is really useful to the community and the church and in which many activities can take place. Hence

 


we’re looking to repair the building and restore it to being a really useful resource to the village and surrounding community.

and we are aiming to do this by 2025 our 800th anniversary

The project will include :

  • putting in a disabled toilet and a kitchenette
  • returning the nave (body of the church) to what we believe it was for 600 years a flexible space, good for varieties of worship, concerts and events. (There will most likely be stackable chairs instead of pews).
  • replacing the roof (it’s currently got old concrete tiles which are beginning to break up, we’re going to put slates on which should last at least 100 years).
  • solving issues of subsidence
  • repairing stonework
  • work on the heating system
  • and improvements to the AV

This should set the building up to be useful for the next 100-200 years by letting much of what is done in it now to be done better It will also open up great opportunities to do so much more here. More, which can help enhance peoples lives in so many, many ways.

 

The Picture below shows the church as it might have been for the first 550 years of it’s life when it had no pews and would have served as a village hall as well as a space for Sunday worship with a ‘sanctuary’ at one end which was kept apart ‘holy’ but the rest used in many ways.

Achieving this is a big challenge as the costs for the full project have been estimated to be £300 000 – £500 000. However we believe this is do-able with the amazing support of  local fund raising and through applications to supportive trusts and other organisations who enable such projects which enhance the life of communities.

We’re phasing the project so that we get maximum impact for the money we raise and can build on the success of each stage. See Project Timeline, right

 

Project
Timeline

2022

Items in BOLD have been achieved and paid for, others on the way and still need more funding to achieve.

Finalise detailed plans
and specifications
(£5500)
Submit planning
applications: (£500)
Obtain quotes and award contracts (£0) –  figures below are estimates until we’ve done this.
 
PHASE 1
Internal works to let us and you get on with using this lovely place better and more.

To be done in these subphases
  • Move Oil Tank
    (£3-5000)
  • remove pews
    level floors
    new chairs
    (£20-30,000)
  •  Install Kitchenette and storage
    (£5-10,000 – Howdens have already agreed to donate kitchen internals)
  • Install disabled toilet, fire exit and pathway lighting
    (£20-30,000)
  • AV upgrade (£3,500)

Phase 1 plans can be found by clicking on this text.

NOTE: if you want further detailed plans and information, please use the Church of England’s online faculty system and search for St Mary’s Hook, or contact the vicar.
 

2023 / 2024

PHASE 2
Structural works to ensure the building is in good condition for the next 100 years (at least)
And activities to make use of the space and enhance the lives of users.
  • Structural and other reports, develop plans, specifications
    and activities
    £10-20,000)
  • planning applications
  • get quotes and award contracts
  • Major repairs to roof, walls, windows, underpin vestry and make other repairs
    (£150-250,000)
  • improve heating and lighting to make more efficient and beautiful
    (£25-30,000)
  • Heritage and other activities organised to make further good use of the building and have positive impact on the community
    (£10,000-100,000)
    These to run over the next five years.